Multiple Choice
Assume a facility is open 8 hours a day and requires an output of 600 units a day. The following tasks must be arranged as an assembly line:
-Considering there are four work centers for the assembly line and assuming 1 worker per work center, calculate the total labor work time.
A) 20 hours per day
B) 25 hours per day
C) 30 hours per day
D) 45 hours per day
E) Need more information to answer the question
Correct Answer:

Verified
Correct Answer:
Verified