Multiple Choice
The process design team at a contract manufacturer in Thailand has broken an assembly process into 8 basic steps, each with a required time and predecessor, as shown in the table. There are 7.5 productive hours available in a day, and the manufacturer wishes to produce 400 units.
-Operations managers and process engineers design a line that contains 6 stations. What is the efficiency?
A) 57.41%
B) 76.54%
C) 65.61%
D) 91.85%
E) Need more information to answer the question
Correct Answer:

Verified
Correct Answer:
Verified
Q22: Assume a facility is open 8 hours
Q23: William is considering a dispatch rule to
Q24: Use the Clark and Wright savings heuristic
Q25: For the Buehler Bakery, the desired output
Q26: Use the Cluster-first-route-second heuristic for two trucks
Q28: Assume that all of the jobs below
Q29: Use the Cluster-first-route-second heuristic for two trucks
Q30: ADAMS Electricals decided to analyze the job
Q31: The process design team at a contract
Q32: Assuming that the customers are ranked