The process design team at a contract manufacturer in Thailand has broken an assembly process into 8 basic steps, each with a required time and predecessor, as shown in the table. There are 7.5 productive hours available in a day, and the manufacturer wishes to produce 400 units.
-Operations managers and process engineers design a line that contains 6 stations. What is the percentage of idle time?
A) 23.46%
B) 42.59%
C) 34.39%
D) 8.15%
E) Need more information to answer the question
Correct Answer:

Verified
Correct Answer:
Verified
Q2: For the Buehler Bakery, the desired output
Q3: For the Buehler Bakery, the desired output
Q4: Assuming that the customers are ranked in
Q5: The following is a sketch of process-focused
Q6: Use the Cluster-first-route-second heuristic for two trucks
Q8: For the Buehler Bakery, the desired output
Q9: Use the Clark and Wright savings heuristic
Q10: William is considering a dispatch rule to
Q11: Use the Cluster-first-route-second heuristic for two trucks
Q12: Use the Cluster-first-route-second heuristic for two trucks