For the Buehler Bakery, the desired output for a 8 hour workday is 450 units. The discrete tasks required to produce the product have been identified, timed in seconds, and ordered as indicated in the table.
-Considering there are 7 work centers for the assembly line and assuming 1 worker per work center, calculate the total labor work time.
A) 56 hours per day
B) 50.62 hours per day
C) 45.63 hours per day
D) 40 hours per day
E) Need more information to answer the question
Correct Answer:

Verified
Correct Answer:
Verified
Q10: William is considering a dispatch rule to
Q11: Use the Cluster-first-route-second heuristic for two trucks
Q12: Use the Cluster-first-route-second heuristic for two trucks
Q13: Use the Cluster-first-route-second heuristic for two trucks
Q14: ADAMS Electricals decided to analyze the job
Q16: ADAMS Electricals has decided to analyze the
Q17: Assume a facility is open 8 hours
Q18: William is considering a dispatch rule to
Q19: Assume that all of the jobs below
Q20: Use the Cluster-first-route-second heuristic for two trucks