For the Buehler Bakery, the Desired Output for a 8

Question 15

Multiple Choice

For the Buehler Bakery, the desired output for a 8 hour workday is 450 units. The discrete tasks required to produce the product have been identified, timed in seconds, and ordered as indicated in the table.
For the Buehler Bakery, the desired output for a 8 hour workday is 450 units. The discrete tasks required to produce the product have been identified, timed in seconds, and ordered as indicated in the table.    -Considering there are 7 work centers for the assembly line and assuming 1 worker per work center, calculate the total labor work time. A) 56 hours per day B) 50.62 hours per day C) 45.63 hours per day D) 40 hours per day E) Need more information to answer the question
-Considering there are 7 work centers for the assembly line and assuming 1 worker per work center, calculate the total labor work time.


A) 56 hours per day
B) 50.62 hours per day
C) 45.63 hours per day
D) 40 hours per day
E) Need more information to answer the question