Multiple Choice
A company has the information shown in the chart below regarding its forecast performance in the past three periods.
-Calculate the running sum of forecast error (RSFE) that provides a measure of forecast bias.
A) -66.67
B) -200.00
C) -300.00
D) 400.00
E) Need more information to answer the question
Correct Answer:

Verified
Correct Answer:
Verified