Rough-cut capacity planning:


A) Utilizes the planned order release from MRP as the source of product demand information.
B) Is completed at the end-item level rather than component level.
C) Uses the actual component routing data rather than using bills of capacity.
D) Is affected by fixed quantity lot-sizing policies used in material requirements planning.