Multiple Choice
Determine the appropriate number of kanbans for the following production scenario:
Production time = .7 hours
Transit time = .5 hours
Wait time = 1.9 hours
Demand per hour = 50 units
Safety stock = 10%
Container size = 20
A) Round up to 17
B) Round up to 9
C) 3.1
D) 2.5
Correct Answer:

Verified
Correct Answer:
Verified