A Manufacturer of Custom Paint and Finishing Products Has an Order

Question 43

Multiple Choice

A manufacturer of custom paint and finishing products has an order for 10,000 gallon cans of a particular sealer. The filling machine will require a total of 120 hours out of 151 hours available to fulfill this order. Cleaning the filling machine between production runs takes 1.2 hours. What is the minimum batch size for the order?


A) 31
B) 322.58
C) 388
D) 37.2