Multiple Choice
A manufacturer of custom paint and finishing products has an order for 10,000 gallon cans of a particular sealer. The filling machine will require a total of 120 hours out of 151 hours available to fulfill this order. Cleaning the filling machine between production runs takes 1.2 hours. What is the minimum batch size for the order?
A) 31
B) 322.58
C) 388
D) 37.2
Correct Answer:

Verified
Correct Answer:
Verified
Q38: A producer of electronic components uses tote
Q39: Match these items.<br>-Kaizen<br>A) Producing items before they
Q40: The type of waste resulting from ineffective
Q41: A producer of molded plastic cases for
Q42: Describe how various approaches to waste minimization
Q44: Facility-focused techniques<br>A) Enable workers to contribute in
Q45: Workforce-focused waste reduction techniques include:<br>A) Cross-training<br>B) Kaizen<br>C)
Q46: Those lean techniques that affect virtually all
Q47: Determine the appropriate number of kanbans for
Q48: Few businesses have succeeded without concentration efforts