The Construction of Toronto's Skydome Took Years of Planning and Construction

Question 94

Multiple Choice

The construction of Toronto's Skydome took years of planning and construction to complete. It is considered to be one of a kind and will suit the various athletic needs of Toronto sports teams for the foreseeable future. The construction of the Skydome can best be described as a/an


A) job-shop system.
B) assembly-line system.
C) project-production system.
D) continuous-flow system.
E) service-flow system.

Correct Answer: