Multiple Choice
In a Design/Bid/Build contractual arrangement, the architect signs a contract with the????
A) Owner
B) Construction manager
C) General contractor
D) Subcontractor
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q3: What is a punch list?<br>A) A card
Q4: Value engineering can best be described
Q5: The ????type of schedule is graphically simple,
Q6: Identify in which listed project phase each
Q7: The architect is most heavily involved during
Q9: In what project phase are the bid
Q10: What is (are) the benefits of meeting
Q11: Which of the estimates listed would occur
Q12: In a guaranteed maximum price contract, costs
Q13: In reporting, a variance can best be