Multiple Choice
The developer of a 40-story high-rise office building desires the shortest possible construction time. What contractual arrangement would be best?
A) Construction management
B) Design/build
C) Design/bid/build
D) Either A or B
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified