    In a Design/Bid/Build Arrangement, a (An) ????Contract Is Most Likely
Solved

In a Design/Bid/Build Arrangement, a (An) ????Contract Is Most Likely

Question 91

Question 91

Multiple Choice

In a Design/Bid/Build arrangement, a (an) ????contract is most likely used between a general contractor and an owner.


A) PCM
B) Owner-build
C) Lump sum
D) Turnkey

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q86: Match the type of schedule listed with

Q87: The developer of a 40-story high-rise office

Q88: Construction managers are usually hired in a

Q89: Identify the person responsible for the following

Q90: Cost codes are used for which of

Q92: If an owner has only a fixed

Q93: Unlike the high-technology industry, the construction industry

Q94: Match the description with the terms listed.Terms

Q95: When compared to other delivery method options,

Q96: Traditionally, concept and feasibility studies are handled

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines