Multiple Choice
Identify in which listed project phase each following project activity would normally occur. Use each phase once only.
-Analyze alternative schemes and conduct engineering analysis
A) Conceptual planning
B) Schematic design
C) Design development
D) Construction documents
E) Bidding and award
Correct Answer:

Verified
Correct Answer:
Verified