Answer the Following Questions Using the Information Below

Question 6

Multiple Choice

Answer the following questions using the information below:
Rana Company planned to use $164 of material per unit but actually used $160 of material per unit, and planned to make 1,200 units but actually made 1,000 units.
-The flexible-budget amount is:


A) $160,000
B) $164,000
C) $196,800
D) $192,000

Correct Answer: