Multiple Choice
Alexandria Engines Incorporated planned to use $37.50 of material per unit but actually used $36.75 of material per unit, and planned to make 1,800 units but actually made 1,600 units.
-The flexible-budget variance is:
A) $1,200 unfavorable
B) $7,500 unfavorable
C) $7,500 favorable
D) $1,200 favorable
Correct Answer:

Verified
Correct Answer:
Verified