If a Call for Tenders Specifically Requires That Certain Work

Question 1

Essay

If a call for tenders specifically requires that certain work be subcontracted out, and that the names of subcontractors that the contractor intends to use be given in the tender, why might a contractor intentionally omit the name of the subcontractor? What are the risks of doing this?