Essay
For Test Bank Problem 7.3, determine (a) the instantaneous symmetrical fault current in kA in phase of the generator as a function of time, assuming maximum dc offset occurs in this generator phase; and (b) the maximum dc offset current in kA as a function of time that can occur in any one generator phase.