Multiple Choice
The post-project review of the Alpha Supplement project is complete. It found failures in planning. Too much time was budgeted to market research, leaving not enough time for product development and quality assurance. As a result, the project could not have succeeded even if the project had been run perfectly. But there were other problems as well. Constant conflicts between team members demonstrated a failure of leadership. Finally, there were failures in controlling. When component providers failed to deliver, project leaders did not locate and train new providers in time. Which of the following is most strongly suggested by the statements above?
A) Most of the conflicts between team members concerned questions of roles and determining who had the authority to make decisions.
B) There were no actions that the project leaders could have taken that would have solved the controlling problems of the Alpha Supplement project.
C) The insufficient time allocated for product development was the only failure related to planning.
D) If the project leaders had located alternate component providers, the Alpha Supplement project still would have failed.
E) The failure of the Alpha Supplement project will make it more difficult for other projects to be approved.
Correct Answer:

Verified
Correct Answer:
Verified
Q261: Since the mid-1980s, Disney's strategic planning group
Q262: A transit supervisor who monitors bus schedules,
Q263: Donna is going to open her own
Q264: Maple Leaf Foods' plan to increase its
Q265: Top managers depend on conceptual skills the
Q266: Mega Computer has a goal of reducing
Q267: Midge thought anxiously about how to position
Q268: The final step in strategy formulation is
Q269: Cecil and Cyrus, two of Simpson's top
Q270: At which level of management are conceptual