Which of the following constitutes a case of anticipatory breach?
A) It occurs when a contracting party fails to inform the other party in advance about nonperformance of his or her contractual duties when due.
B) In case of anticipatory breach, nonbreaching party's obligations under the contract are not discharged.
C) The nonbreaching party must wait until performance is due to sue the breaching party.
D) Anticipatory breach can be derived from the conduct of the breaching party without being expressly stated by that party.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: QuickClicks, an online advertising company, makes a
Q8: A court order that prohibits a person
Q20: An unconditional and absolute offer by a
Q29: Specific performance of personal service contracts is
Q47: If the builder breaches a construction contract
Q55: When a party commits an anticipatory breach,
Q70: _ is a situation in which a
Q77: An award of _ orders the breaching
Q78: Mary buys a new toaster for $500.
Q82: An employee who has been dismissed improperly