    If an Activity's Optimistic Time Is Four Days, Its Realistic
Solved

If an Activity's Optimistic Time Is Four Days, Its Realistic

Question 91

Question 91

True/False

If an activity's optimistic time is four days, its realistic time is 10 days, and its pessimistic time is 25 days, then its estimated time would be 11.5 days.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q48: The status report project team communication method

Q84: Gantt charts visually show the time overlap

Q84: Arguably, the most instrumental person to the

Q85: Defining the necessary activities required to organize

Q86: Gantt charts do not show how tasks

Q87: What would be the estimated time for

Q89: COCOMO uses parameters that are derived from

Q92: Optimistic time refers to:<br>A) the maximum period

Q93: Ensuring that all contractual terms of the

Q94: A scheduling technique where the order and

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines