True/False
If an activity's optimistic time is four days, its realistic time is 10 days, and its pessimistic time is 25 days, then its estimated time would be 11.5 days.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q48: The status report project team communication method
Q84: Gantt charts visually show the time overlap
Q84: Arguably, the most instrumental person to the
Q85: Defining the necessary activities required to organize
Q86: Gantt charts do not show how tasks
Q87: What would be the estimated time for
Q89: COCOMO uses parameters that are derived from
Q92: Optimistic time refers to:<br>A) the maximum period
Q93: Ensuring that all contractual terms of the
Q94: A scheduling technique where the order and