Multiple Choice
A scheduling technique where the order and duration of the sequence of activities directly affect the completion date of a project refers to:
A) sequencing strategy.
B) Gantt scheduling.
C) critical path scheduling.
D) activity scheduling.
E) task management.
Correct Answer:

Verified
Correct Answer:
Verified