Multiple Choice
An individual with a diverse set of skills-management, leadership, technical, conflict management, and customer relationship-who is responsible for initiating, planning, executing, and closing down a project best defines:
A) chief information officer.
B) consultant.
C) project scheduler.
D) project manager.
E) end user.
Correct Answer: