Multiple Choice
An online or hard-copy repository for all project correspondence, inputs, outputs, deliverables, procedures, and standards that is used for performing project audits, orientation of new team members, communicating with management and customers, identifying future projects, and performing post project reviews is called:
A) a project workbook.
B) a schedule book.
C) a project planner.
D) project management software.
E) an electronic calendar.
Correct Answer:

Verified
Correct Answer:
Verified