Which of the following is NOT a project planning activity?
A) Setting a baseline project plan
B) Identifying and assessing risk
C) Determining project standards and procedures
D) Establishing management procedures
E) Developing a project charter
Correct Answer:

Verified
Correct Answer:
Verified