Multiple Choice
The third phase of the project management process in which the plans created in the prior phases are put into action is:
A) project planning.
B) project development.
C) project initiation.
D) project execution.
E) project close down.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q12: During project initiation, the focus of developing
Q13: The meetings project team communication method has
Q14: Which of the following is NOT a
Q15: The process of dividing the project into
Q18: The responsibility for keeping all team members
Q19: Which of the following is NOT a
Q20: The Constructive Cost Model is a method
Q21: What would be the estimated time for
Q22: Which of the following states correctly the
Q101: A network diagram depicts project tasks and