Which of the following is a True statement regarding project time estimates?
A) Project time estimates for task completion and overall system quality are significantly influenced by the assignment of people to tasks.
B) Resource estimates should not be revised based upon the skills of the actual person assigned to a particular activity.
C) Staff learning can be enhanced by assigning individuals to tasks which are "over their heads."
D) Project time estimates are always on target.
E) Hardware and software are the most important, and expensive, part of project resource planning.
Correct Answer:

Verified
Correct Answer:
Verified
Q4: Realistic time refers to:<br>A) the maximum period
Q5: Changes to the baseline project plan might
Q6: The amount of time that an activity
Q12: During project initiation, the focus of developing
Q13: The meetings project team communication method has
Q17: A logic model is a graphical representation
Q25: The focus of closing the customer contract
Q59: The ability to easily make changes to
Q126: A project can terminate naturally or unnaturally.
Q154: The most instrumental person to the successful