The amount of time that an activity can be delayed without delaying the project refers to:


A) noncritical time.
B) slack time.
C) down time.
D) delay time.
E) stop time.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: Which of the following project management activities

Q2: Any person, group of people, piece of

Q4: Realistic time refers to:<br>A) the maximum period

Q5: Changes to the baseline project plan might

Q8: Which of the following is a True

Q17: A logic model is a graphical representation

Q25: The focus of closing the customer contract

Q59: The ability to easily make changes to

Q126: A project can terminate naturally or unnaturally.

Q154: The most instrumental person to the successful

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines