Multiple Choice
A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task best defines:
A) Gantt.
B) Computer Aided Software Engineering (CASE) .
C) Program Evaluation Review Technique (PERT) .
D) flowcharting.
E) Unified Modeling Language (UML) .
Correct Answer:

Verified
Correct Answer:
Verified