    What Would Be the Estimated Time for Completion If Time
Solved

What Would Be the Estimated Time for Completion If Time

Question 36

Question 36

Multiple Choice

What would be the estimated time for completion if time estimates for programming are as follows? optimistic = 4 weeks; pessimistic = 6 weeks; realistic = 5 weeks


A) 5 weeks
B) 6 weeks
C) 15 weeks
D) 3 weeks
E) 30 weeks

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q32: Which of the following is NOT a

Q34: A technique that uses optimistic, pessimistic, and

Q35: Automated tools available to help you manage

Q38: The project workbook serves as a repository

Q39: Skills that include defining and sequencing activities,

Q40: A baseline project plan is developed during

Q41: A slipped completion date for an activity

Q92: A systems development project may be undertaken

Q111: A resource analysis plan determines if the

Q124: Project planning is the first phase of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines