Multiple Choice
Which of the following statements regarding project management is False?
A) Gantt charts give a timeline for each of a project's activities, but they do not adequately illustrate the interrelationships between the activities and the resources.
B) A project organization works best for a project that is temporary but critical to the organization.
C) A project organization works well when the work contains simple, independent tasks.
D) Gantt charts and PERT/CPM are never used together.
E) All of the above are False.
Correct Answer:

Verified
Correct Answer:
Verified
Q14: Every network has at least one critical
Q32: PERT calculations typically include the duration variance
Q34: The Beta distribution is used in project
Q35: What is the basic difference between PERT
Q39: Which of the following statements regarding CPM
Q47: One phase of a large project is
Q72: What is the objective of critical path
Q80: A code of ethics especially for project
Q97: A project organization works best for an
Q120: How is the expected completion time of