Multiple Choice
The Beta distribution is used in project management to
A) determine which activity should be crashed
B) calculate the probability that a project will be completed within its budget
C) calculate expected activity times
D) calculate slack for activities on the critical path
E) none of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q14: Every network has at least one critical
Q29: The network below represents a project being
Q32: PERT calculations typically include the duration variance
Q35: Which of the following statements regarding project
Q35: What is the basic difference between PERT
Q39: Which of the following statements regarding CPM
Q47: One phase of a large project is
Q72: What is the objective of critical path
Q80: A code of ethics especially for project
Q120: How is the expected completion time of