Consider the network pictured below.
a. Enumerate all paths through this network.
b. Calculate the critical path for the network.
c. What is the minimum duration of the project?
d. How much slack exists at each activity?
Correct Answer:

Verified
(a) Possible paths are P-S (length 22), ...View Answer