Multiple Choice
Which of these statements regarding time-cost tradeoffs in CPM networks is true?
A) Crashing is not possible unless there are multiple critical paths.
B) Crashing a project often reduces the length of long-duration, but noncritical, activities.
C) Activities not on the critical path can never be on the critical path, even after crashing.
D) Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
E) None of the above is true.
Correct Answer:

Verified
Correct Answer:
Verified
Q10: A partially solved PERT problem is
Q17: Given the project within the table
Q18: Consider the network described in the
Q20: A project being analyzed by PERT has
Q28: What is a project organization?
Q66: Identify, in order, the six steps basic
Q75: Analysis of a PERT problem shows the
Q87: What are the earliest activity start time
Q89: The fundamental difference between PERT and CPM
Q110: Which of the following statements regarding Gantt