Given the Project Within the Table Below Calculate
A

Question 17

Essay

Given the project within the table below calculate
a. The critical path
b. The minimum project duration
c. The amount of slack for each activity
 Activity  Duration  (hours)  Immediate  Predecessors A4 None B3 None C10 None D7 B,CE1DF1EG5 A, F\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Duration } \\\text { (hours) }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} \\\hline \mathrm{A} & 4 & \text { None } \\\hline \mathrm{B} & 3 & \text { None } \\\hline \mathrm{C} & 10 & \text { None } \\\hline \mathrm{D} & 7 & \mathrm{~B}, \mathrm{C} \\\hline \mathrm{E} & 1 & \mathrm{D} \\\hline \mathrm{F} & 1 & \mathrm{E} \\\hline \mathrm{G} & 5 & \mathrm{~A}, \mathrm{~F} \\\hline\end{array}

Correct Answer:

verifed

Verified

blured image
(A) The critical path is CDEFG
(B) Min...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions