Multiple Choice
Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity _________ should be crashed first, adding _________ to project cost.
A) B; $2,000
B) B; $8,000
C) C; $1,000
D) C; $2,000
E) C; $6,000