Two Critical Path Activities Are Candidates for Crashing on a CPM

Question 96

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity _________ should be crashed first, adding _________ to project cost.  Activity  Normal Time  Normal Cost  Crash Time  Crash Cost  B 4 days $6,0003 days $8,000 C 6 days $4,0004 days $6,000\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \text { Normal Time } & \text { Normal Cost } & \text { Crash Time } & \text { Crash Cost } \\\hline \text { B } & 4 \text { days } & \$ 6,000 & 3 \text { days } & \$ 8,000 \\\hline \text { C } & 6 \text { days } & \$ 4,000 & 4 \text { days } & \$ 6,000 \\\hline\end{array}


A) B; $2,000
B) B; $8,000
C) C; $1,000
D) C; $2,000
E) C; $6,000