Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.
a. What is the crash cost per unit time for activity A?
b. What is the crash cost per unit time for activity B?
c. Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
d. Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?
e. Assuming no other paths become critical, how much can this project be shortened at what total added cost?
Correct Answer:

Verified
(a) $2,000; (b) $4,0...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q35: Which of the following statements regarding critical
Q40: Explain why the critical path is the
Q47: Work Breakdown Structure is a useful tool
Q48: A local project being analyzed by PERT
Q49: Two critical path activities are candidates
Q50: Which of the following statements regarding time-cost
Q53: Ethical issues which can arise in projects
Q55: Briefly describe the concept of cost/time trade-off
Q57: The project organization works best when which
Q74: A combination of effective Gantt chart use