Multiple Choice
Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity __________ should be crashed first, adding __________ to project cost.
A) One; $400
B) One; $6,800
C) Two; $1,000
D) Two; $5,000
E) One or two should be crashed; $1,400