Draw the AOA and AON Networks for the Following Project

Question 23

Essay

Draw the AOA and AON networks for the following project and calculate the minimum project duration.
 Activity  Duration  (days)  Immediate  Predecessors  A 10 B 8 C 2 A D 4 A E 5 B,C,D\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Duration } \\\text { (days) }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} \\\hline \text { A } & 10 & - - \\\hline \text { B } & 8 & - - \\\hline \text { C } & 2 & \mathrm {~A} \\\hline \text { D } & 4 & \mathrm {~A} \\\hline \text { E } & 5 & \mathrm {~B} , \mathrm { C } , \mathrm { D } \\\hline\end{array}

Correct Answer:

verifed

Verified

AON
blured image
AOA
blured image Minimum...