Essay
A facility is trying to set up an assembly line, and has identified the various tasks, and their relationship to each other, as shown in the following table. They wish to produce 600 units per day, working two 8-hour shifts.
a. Draw a network diagram of precedence relationships.
b. Compute the required cycle time per unit in seconds.
c. Compute the minimum number of workstations required to produce 600 units per day.
d. Balance this line using longest processing time.
e. What is the efficiency of the line obtained in part d?
Correct Answer:

Verified
(a) The precedence diagram appears below...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q55: _ is the maximum time that the
Q57: Which of the following is not a
Q58: Category management is the use of computer
Q59: If the schedule calls for the production
Q61: Which of the following is not one
Q62: One of the major advantages of process-oriented
Q63: An assembly line is assigned as follows.
Q65: The typical goal used when developing a
Q221: A(n) _ addresses flow, allocates space, and
Q278: Heuristics are problem-solving procedures that mathematically optimize