Essay
An assembly line is assigned as follows. Station A- task A, B, and C. Station B- task D. Station C- task E and F. The task times are 7, 3, 2, 9, 4, and 5 minutes respective to A, B, C, D, E, and F. (Assume that there is no precedence relationships between the tasks, ie they can be accomplished in any order)
A. Calculate the efficiency.
B. What would the assignment of tasks to stations be using shortest processing time (assuming the current maximum station time remains the cycle time)?
Correct Answer:

Verified
Efficiency= Sum of task time / (# Statio...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q58: Category management is the use of computer
Q59: If the schedule calls for the production
Q60: A facility is trying to set
Q61: Which of the following is not one
Q62: One of the major advantages of process-oriented
Q65: The typical goal used when developing a
Q68: Which type of layout is specifically designed
Q221: A(n) _ addresses flow, allocates space, and
Q254: A production line is to be designed
Q289: The most common tactic to arrange departments