A Methods and Measurements Analyst needs to develop a time standard for a certain task. The task involves use of ruler, square, and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction). In a preliminary study, he observed one of his workers perform this task five times. The observations were made in an air-conditioned, well-lighted training facility, at ground level, with all tools and equipment clean and readily available.
a. What is the actual average time for this task?
b. What is the normal time for this task if the employee worked at a 20% faster pace than is typical for adequately trained workers?
c. What is standard time for this task if allowances are 8% constant and 6% variable?
d. If the analyst then thought more carefully about his experiment, and decided that the variable allowances needed to be increased to match the real (outside, unair-conditioned) work environment, and that the proper variable allowance was not 6% but 12%, what is the revised standard time?
Correct Answer:

Verified
a. Actual average time is 79 s...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q17: Most unions do not accept the use
Q76: In a stopwatch time study, the average
Q77: A task involves positioning two metal
Q78: In a preliminary work sample of an
Q79: Most pit crew members have background experience
Q80: Which of the following statements regarding incentive
Q82: "Designed to show economy of motion by
Q84: Psychological factors have little relevance in the
Q85: In a large aerospace company, it has
Q86: Provide examples of non-monetary incentives.