Question 79

Multiple Choice

A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are: A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:   If the company wants the output rate to be equal to demand, what is the desired cycle time (in seconds) ? A)  162 B)  72 C)  54 D)  12 E)  60
If the company wants the output rate to be equal to demand, what is the desired cycle time (in seconds) ?


A)  162
B)  72
C)  54
D)  12
E)  60