Multiple Choice
Which of the following is a direct input into capacity requirements planning?
(I) the master production schedule
(II) routing information
(III) current shop loads
(IV) planned-order releases
A) II, III, and IV only
B) I, II, and IV only
C) I, III, and IV only
D) I and II only
E) I, II, III, and IV
Correct Answer:

Verified
Correct Answer:
Verified
Q69: The identification of parent items that have
Q70: The gross requirements value for any given
Q71: In MRP, EOQ models tend to be
Q72: A bill of materials contains a listing
Q73: In a master schedule, the planning horizon
Q75: Capacity requirements planning helps managers reconcile _
Q76: The inventory records contain information on the
Q77: MRP output reports are divided into two
Q78: MRP is used within MRP II systems.
Q79: Which one of the following most closely