Multiple Choice
The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows:
Assume there must be one-to-one matching between consultants and projects. In how many different ways can she assign these consultants to these projects?
A) 4
B) 8
C) 16
D) 24
E) 256
Correct Answer:

Verified
Correct Answer:
Verified
Q6: A major difference between manufacturing and service
Q22: There are four resources and four
Q24: Which of the following is not an
Q25: The president of a consulting firm wants
Q27: Organizations with fixed, perishable capacity can benefit
Q31: In theory of constraints scheduling, the synchronization
Q50: The Hungarian method is limited to a
Q53: In theory of constraints scheduling, the _
Q70: Scheduling in intermediate-volume systems has three basic
Q78: A schedule chart depicts the loading and