What would be the estimated time for completion if the time estimates for report design are as follows? optimistic = 3 weeks; pessimistic = 9 weeks; realistic = 6 weeks
A) 3 weeks
B) 5 weeks
C) 36 weeks
D) 6 weeks
E) 18 weeks
Correct Answer:

Verified
Correct Answer:
Verified