Multiple Choice
Which of the following is true regarding Gantt chart construction?
A) Squares are used to represent activities.
B) To construct the Gantt chart, a horizontal bar is drawn for each activity that reflects its sequence and duration.
C) To show precedence relationships, arrows are used to connect the nodes.
D) Arrows are used to reflect the sequence of activities.
E) Ellipses are used to represent activities.
Correct Answer:

Verified
Correct Answer:
Verified