Based on the Optimistic, Realistic, and Pessimistic Time Estimates Provided

Question 66

Multiple Choice

Based on the optimistic, realistic, and pessimistic time estimates provided, determine the expected time.(Estimates are based on weeks.)
-Optimistic = 4; realistic = 6; pessimistic = 10


A) 1 week
B) 6 weeks
C) 5 weeks
D) 6.33 weeks
E) 3 weeks

Correct Answer: