    Which of the Following Is an Implicit Environmental Cost
Solved

Which of the Following Is an Implicit Environmental Cost

Question 72

Question 72

Multiple Choice

Which of the following is an implicit environmental cost?


A) direct costs of modifying technology and processes
B) costs of cleanup and disposal
C) fines levied by government agencies
D) costs of legal counsel and administration

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q62: Emerging customer needs are assessed and ideas

Q63: What are some nonfinancial measures that a

Q64: Total-life-cycle costing is the name given to:<br>A)a

Q65: The objective to discover and develop new,more

Q66: After conducting a market research study, Stewart

Q67: The objective to reduce product development cycle

Q68: The relevance of information in a MACS

Q69: The post-sale service and disposal cycle of

Q70: Target costing is:<br>A)customer-driven.<br>B)value-driven.<br>C)engineering-driven.<br>D)market-driven.

Q71: Breakeven time measures the length of time

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines