Devon Construction Inc

Question 74

Multiple Choice

Devon Construction Inc. is currently in the midst of a residential construction project. The company's operations manager realizes that certain phases of the project are behind schedule due to unavailability of raw materials. Which of the following tools should Devon's operations manager use to better manage project scheduling?


A) The SWOT matrix
B) The critical path method
C) Computer-aided design software
D) Vertical integration