A Requirement of Top-Down Budgeting Is

Question 20

Multiple Choice

A requirement of top-down budgeting is:


A) involvement of the project team
B) estimating the detailed level of the project's tasks
C) applying the learning curve to labor time estimates
D) all of the above
E) none of the above